8projects·$4.6Mfederal of $13.0M eligible
Ear Falls Multiplex
$2.7MEar Falls · Recreation
complete·approved 2009
Water Treatment Plant and Low Lift Pumping Station Assessment and Rehabilitation
$977.2KEar Falls · Drinking Water
underway·approved 2022
Rehabilitation of Eight Ear Falls Roads
$490.0KEar Falls · Highways and Roads
complete·approved 2005
Clarifier Rehabilitation at the Ear Falls Wastewater Treatment Plant
$225.9KEar Falls · Wastewater
complete·approved 2017
Accessibility Rehabilitation of Recreational Centre
$92.4KEar Falls · Recreation
complete·approved 2021
Trail Development
$80.0KEar Falls · Active Transportation
complete·approved 2021
Waterfront and Trail Revitalization
$33.2KEar Falls · Active Transportation
complete·approved 2022
Ear Falls Asset Management Program
$3.7KEar Falls · Capacity Building
complete·approved 2007
| Project | Location | Category | Status | Federal | Total | Approved |
|---|---|---|---|---|---|---|
| Ear Falls Multiplex Township of Ear Falls | Ear Falls | Recreation | complete | $2.7M | $8.1M | 2009 |
| Water Treatment Plant and Low Lift Pumping Station Assessment and Rehabilitation Township of Ear Falls | Ear Falls | Drinking Water | underway | $977.2K | $2.4M | 2022 |
| Rehabilitation of Eight Ear Falls Roads Township of Ear Falls | Ear Falls | Highways and Roads | complete | $490.0K | $1.5M | 2005 |
| Clarifier Rehabilitation at the Ear Falls Wastewater Treatment Plant Township of Ear Falls | Ear Falls | Wastewater | complete | $225.9K | $464.1K | 2017 |
| Accessibility Rehabilitation of Recreational Centre Township of Ear Falls | Ear Falls | Recreation | complete | $92.4K | $231.0K | 2021 |
| Trail Development Township of Ear Falls | Ear Falls | Active Transportation | complete | $80.0K | $100.0K | 2021 |
| Waterfront and Trail Revitalization Township of Ear Falls | Ear Falls | Active Transportation | complete | $33.2K | $152.6K | 2022 |
| Ear Falls Asset Management Program Township of Ear Falls | Ear Falls | Capacity Building | complete | $3.7K | $11.1K | 2007 |