Whitehorse Hillcrest Reconstruction (Phase 1A)
Federal contribution
$2.0M
$2,036,278
Federal share75%
of $2.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 21, 2025
today
20252026
BuiltForecast
Approved 11 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- City of Whitehorse
- Construction start
- May 27, 2025(actual)
- Construction end
- Oct 31, 2026(forecast)
Also in Whitehorse
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. How to read these figures.