Yukon Green Energy Legacy
Federal contribution
$71.0M
$71,000,000
Federal share50%
of $142.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 29, 2009
201020112012
Built
Approved 2 weeks before the announcement.
- Program
- Green Infrastructure Fund
- Ultimate recipient
- Yukon Energy Corporation
- Construction start
- Jun 4, 2010(actual)
- Construction end
- Dec 23, 2011(actual)
Against the original forecast
- Construction end12 months earlyforecast Dec 31, 2012
Also in Whitehorse
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39353 in the federal list. How to read these figures.