Kwanlin Dun First Nation Community Hub

Whitehorse, Yukon

completeRecreationRNIS
Federal contribution
$15.0M
$15,000,000
Federal share75%

of $20.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 3, 2019
20202021
Built

Approved 3 weeks before the announcement.

Program
Rural & Northern Infrastructure Stream
Ultimate recipient
Kwanlin Dun First Nation
Construction start
Sep 5, 2019(actual)
Construction end
Oct 29, 2021(actual)

Against the original forecast

  • Construction end4 weeks lateforecast Sep 30, 2021