Scarborough Subway Extension
Federal contribution
$1.1B
$1,127,654,475
Federal share40%
of $2.8B total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 11, 2021
20222023
BuiltForecast
- Program
- Public Transit Infrastructure Stream
- Ultimate recipient
- Metrolinx
- Construction start
- Jun 1, 2021(actual)
- Construction end
- Mar 31, 2023(forecast)
Against the original forecast
- Construction start6 months earlyforecast Dec 1, 2021