Port Lands Flood Protection and Enabling Infrastructure

Toronto, Ontario

underwayBrownfield Remediation And RedevelopmentTWRI
Federal contribution
$384.2M
$384,166,667
Federal share30%

of $1.3B total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 28, 2017
2018202020222024
BuiltForecast
Program
Toronto Waterfront Revitalization Initiative
Construction start
Nov 28, 2018(actual)
Construction end
Dec 31, 2024(forecast)

Against the original forecast

  • Construction start11 months lateforecast Jan 1, 2018

Also in Toronto

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51547 in the federal list. How to read these figures.