Back to projects

Edmonton Valley Line West Light Rail Transit (LRT)

Edmonton, Alberta

underwayPublic TransitGIS
Federal contribution
$199.8M
$199,756,871
Federal share40%

of $499.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 11, 2019
today
20192021202320252027
BuiltForecast
Program
Green Infrastructure Stream
Ultimate recipient
City of Edmonton
Construction start
Dec 22, 2020(actual)
Construction end
Jun 15, 2028(forecast)

Also in Edmonton