Royal Alberta Museum
Federal contribution
$112.5M
$112,500,000
Federal share48%
of $234.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedNov 16, 2011
201220132014201520162017
Built
- Program
- Building Canada Fund - Major Infrastructure Component
- Ultimate recipient
- Government of Alberta
- Construction start
- Jul 30, 2012(actual)
- Construction end
- Nov 15, 2016(actual)
Against the original forecast
- Construction start4 months earlyforecast Nov 30, 2012
- Construction end4 months lateforecast Jul 31, 2016
Also in Edmonton
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29839 in the federal list. How to read these figures.