Reconstruction of Line 3 North Bridge

Bonfield, Ontario

completeHighways and RoadsMRIF
Federal contribution
$101,827
Federal share33%

of $305.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 25, 2005
200620072008
Built
Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Township of Bonfield
Construction start
Apr 26, 2005(actual)
Construction end
Oct 31, 2008(actual)

Against the original forecast

  • Construction end7 months lateforecast Mar 31, 2008