Trunk Road Reconstruction

Bonfield, Ontario

completeHighways and RoadsISF
Federal contribution
$315,703
Federal share33%

of $950.5K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Township of Bonfield
Construction start
Sep 28, 2009(actual)
Construction end
Mar 31, 2011(actual)

Against the original forecast

  • Construction start5 weeks earlyforecast Nov 1, 2009

Also in Bonfield

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 32249 in the federal list. How to read these figures.