Replacement of the Strathroy-Caradoc water supply system
Federal contribution
$4.5M
$4,452,111
Federal share33%
of $13.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 25, 2005
20062007
Built
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Township of Strathroy-Caradoc
- Construction start
- Apr 20, 2005(actual)
- Construction end
- Mar 30, 2007(actual)
Against the original forecast
- Construction start5 months lateforecast Nov 15, 2004
- Construction end6 months lateforecast Sep 30, 2006
Also in Strathroy
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 11457 in the federal list. How to read these figures.