Construction of Kerwood wastewater collection system
Federal contribution
$998,392
Federal share33%
of $3.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 25, 2005
200620072008200920102011
Built
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Township of Adelaide Metcalfe
- Construction start
- May 1, 2005(actual)
- Construction end
- Oct 31, 2010(actual)
Against the original forecast
- Construction end5 months earlyforecast Mar 31, 2011
Also in Strathroy
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 11789 in the federal list. How to read these figures.