Rehabilitation and Replacement of Three Bridges
Federal contribution
$885,000
Federal share33%
of $2.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 25, 2005
200620072008
Built
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- County of Renfrew
- Construction start
- Apr 20, 2005(actual)
- Construction end
- Mar 25, 2008(actual)
Against the original forecast
- Construction start5 months lateforecast Nov 15, 2004
- Construction end5 months lateforecast Oct 31, 2007
Also in Pembroke
- HVAC System UV Treatment; HVAC Duct Sealing; Ventilation$2.2M
- Reconstruction of a Section of Pembroke Street West$2.0M
- Bennet Street and Boundary Road Watermain Replacement and Taylor Bridge Watermain Suspension$1.9M
- HVAC Upgrades; Portable Replacement; Installation of Bottle Filling Stations$1.5M
- Algonquin Trail North Active Transportation Enhancements$1.5M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 11512 in the federal list. How to read these figures.