Rehabilitation of bridges, underpass, culverts and reconstruction of roads
Federal contribution
$6.9M
$6,933,333
Federal share33%
of $20.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 25, 2005
20062007200820092010
Built
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- City of Greater Sudbury
- Construction start
- Apr 21, 2005(actual)
- Construction end
- Feb 22, 2010(actual)
Against the original forecast
- Construction start3 weeks lateforecast Apr 1, 2005
- Construction end11 months lateforecast Mar 31, 2009
Also in Greater Sudbury
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 11517 in the federal list. How to read these figures.