Rehabilitation of Development Road West

New Liskeard, Ontario

completeHighways and RoadsMRIF
Federal contribution
$86,181
Federal share33%

of $258.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 25, 2005
20062007
Built
Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Township of Harley
Construction start
Jun 1, 2005(actual)
Construction end
Dec 18, 2006(actual)

Against the original forecast

  • Construction start4 weeks earlyforecast Jul 1, 2005
  • Construction end3 months lateforecast Sep 30, 2006

Also in New Liskeard