Construction of a Biofuel Pellet Plant

New Liskeard, Ontario

completeGreen EnergyCC
Federal contribution
$1.5M
$1,458,750
Federal share25%

of $5.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 13, 2009
2009201120132015
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
KD Logging
Construction start
Jan 1, 2010(actual)
Construction end
Dec 10, 2015(actual)

Against the original forecast

  • Construction start9 months lateforecast Apr 1, 2009
  • Construction end3 weeks earlyforecast Dec 31, 2015