Rehabilitation of Barrie Hill Bridge

Guelph, Ontario

completeHighways and RoadsMRIF
Federal contribution
$268,891
Federal share33%

of $806.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 25, 2005
Built
Program
Municipal Rural Infrastructure Fund
Ultimate recipient
County of Wellington
Construction start
Apr 20, 2005(actual)
Construction end
Nov 28, 2005(actual)

Against the original forecast

  • Construction start2 months earlyforecast Jun 20, 2005
  • Construction end4 weeks lateforecast Oct 31, 2005

Also in Guelph

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 11575 in the federal list. How to read these figures.