Transit Bus Replacement: 24 conventional buses, 9 specialized vehicles.
Federal contribution
$7.3M
$7,269,195
Federal share49%
of $14.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 31, 2017
20172018
Built
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- The Corporation of The City of Guelph
- Construction start
- Apr 1, 2016(actual)
- Construction end
- Aug 20, 2018(actual)
Against the original forecast
- Construction end5 months lateforecast Mar 31, 2018