Bus Fleet Electrification
Federal contribution
$4.5M
$4,538,803
Federal share40%
of $11.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 16, 2020
2020202220242026
BuiltForecast
- Program
- Public Transit Infrastructure Stream
- Ultimate recipient
- The Corporation of The City of Guelph
- Construction start
- Jun 1, 2021(actual)
- Construction end
- Mar 31, 2026(forecast)
Also in Guelph