Rehabilitation of Greenbrook Plaza Bridge
Federal contribution
$66,337
Federal share33%
of $199.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 25, 2005
2006200720082009
Built
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- City of Kitchener
- Construction start
- Jan 2, 2006(actual)
- Construction end
- Sep 23, 2009(actual)
Against the original forecast
- Construction end3 years lateforecast Sep 30, 2006
Also in Kitchener
- Stormwater Network Adaptation$50.0M
- Aquatic Centre RBJ Schlegel Park$9.8M
- Installing mechanical ventilation in buildings where none currently exist; Window repair or replacement for fresh air intake$7.9M
- HVAC Upgrades; Upgrading wireless access points; Window replacement; Washroom upgrades; Installing cooling / air conditioning units; room partition replacement$7.6M
- Kitchener Public Library Southwest Community Library$6.0M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 11624 in the federal list. How to read these figures.