Upgrading of Belleville Water Pollution Control Plant
Federal contribution
$644,167
Federal share33%
of $1.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 25, 2005
2006200720082009
Built
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- City of Belleville
- Construction start
- May 1, 2005(actual)
- Construction end
- Aug 13, 2009(actual)
Against the original forecast
- Construction end2.6 years lateforecast Dec 31, 2006