Rehabilitation and replacement of three bridges

Cobourg, Ontario

completeHighways and RoadsMRIF
Federal contribution
$338,333
Federal share33%

of $1.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 25, 2005
200620072008
Built
Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Township of Hamilton
Construction start
Apr 20, 2005(actual)
Construction end
May 10, 2008(actual)

Against the original forecast

  • Construction start5 months lateforecast Dec 2, 2004
  • Construction end22 months lateforecast Jun 30, 2006

Also in Cobourg

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 11656 in the federal list. How to read these figures.