Rehabilitation and replacement of three bridges
Federal contribution
$338,333
Federal share33%
of $1.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 25, 2005
200620072008
Built
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Township of Hamilton
- Construction start
- Apr 20, 2005(actual)
- Construction end
- May 10, 2008(actual)
Against the original forecast
- Construction start5 months lateforecast Dec 2, 2004
- Construction end22 months lateforecast Jun 30, 2006
Also in Cobourg