Upgrading to Alternate 401 Detour Route
Federal contribution
$2.0M
$1,953,512
Federal share33%
of $5.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 5, 2009
20102011
Built
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- County of Northumberland
- Construction start
- Aug 31, 2009(actual)
- Construction end
- Oct 15, 2011(actual)
Against the original forecast
- Construction end2 weeks earlyforecast Oct 31, 2011