Back to projects

D’Arcy Street Reconstruction

Cobourg, Ontario

completeHighways and RoadsISF
Federal contribution
$1.1M
$1,050,000
Federal share33%

of $3.1M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Town of Cobourg
Construction start
May 31, 2010(actual)
Construction end
Jun 30, 2011(actual)

Against the original forecast

  • Construction start2 weeks lateforecast May 15, 2010
  • Construction end4 weeks lateforecast Jun 1, 2011

Also in Cobourg