Replacement of Government Road Bridge over Anderson Creek
Federal contribution
$70,000
Federal share33%
of $210.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 25, 2005
2006
Built
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Township of Tarbutt and Tarbutt Additional
- Construction start
- May 1, 2005(actual)
- Construction end
- Jan 17, 2006(actual)
Against the original forecast
- Construction end4 months lateforecast Sep 30, 2005
Also in Desbarats
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 11662 in the federal list. How to read these figures.