Replacement of Gordon Lake Road Bridge

Desbarats, Ontario

completeHighways and RoadsCC
Federal contribution
$111,144
Federal share33%

of $333.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 13, 2009
2010
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
Township of Johnson
Construction start
Jul 1, 2009(actual)
Construction end
Dec 31, 2009(actual)

Against the original forecast

  • Construction end10 months earlyforecast Oct 31, 2010

Also in Desbarats

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 24649 in the federal list. How to read these figures.