Upgrading of Marmora Water Pollution Control Plant
Federal contribution
$966,667
Federal share33%
of $2.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 25, 2005
2006200720082009
Built
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Municipality of Marmora and Lake
- Construction start
- Apr 20, 2005(actual)
- Construction end
- Apr 24, 2009(actual)
Against the original forecast
- Construction start5 months lateforecast Nov 15, 2004
- Construction end2.5 years lateforecast Oct 31, 2006
Also in Marmora
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 11692 in the federal list. How to read these figures.