Upgrading of Marmora Water Pollution Control Plant

Marmora, Ontario

completeWastewaterMRIF
Federal contribution
$966,667
Federal share33%

of $2.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 25, 2005
2006200720082009
Built
Program
Municipal Rural Infrastructure Fund
Construction start
Apr 20, 2005(actual)
Construction end
Apr 24, 2009(actual)

Against the original forecast

  • Construction start5 months lateforecast Nov 15, 2004
  • Construction end2.5 years lateforecast Oct 31, 2006