Replacement of Ackerman Bridge and Bronson's Bridge

Marmora, Ontario

completeHighways and RoadsMRIF
Federal contribution
$309,833
Federal share33%

of $929.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 21, 2006
20072008
Built
Program
Municipal Rural Infrastructure Fund
Construction start
May 6, 2006(actual)
Construction end
Mar 19, 2008(actual)

Against the original forecast

  • Construction end4 months lateforecast Nov 15, 2007

Also in Marmora

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 13957 in the federal list. How to read these figures.