Reconstruction of Black's Bridge
Federal contribution
$500,000
Federal share33%
of $1.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 25, 2005
200620072008
Built
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- County of Dufferin
- Construction start
- Apr 20, 2005(actual)
- Construction end
- Nov 29, 2007(actual)
Against the original forecast
- Construction start2 months lateforecast Feb 5, 2005
- Construction end17 months lateforecast Jun 30, 2006
Also in Orangeville
- Dufferin County Administration and Provincial Offences Court Addition$2.7M
- Upgrading of the Water Pollution Control Plant$2.4M
- Rehabilitation of the West Sector Reservoir$2.0M
- Reconstruction of Roads and Services in the South Park and Village Green Subdivisions$1.6M
- New Transfer Terminal and Bus Acquisition$1.0M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 11746 in the federal list. How to read these figures.