Back to projects

Reconstruction of Black's Bridge

Orangeville, Ontario

completeHighways and RoadsMRIF
Federal contribution
$500,000
Federal share33%

of $1.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 25, 2005
200620072008
Built
Program
Municipal Rural Infrastructure Fund
Ultimate recipient
County of Dufferin
Construction start
Apr 20, 2005(actual)
Construction end
Nov 29, 2007(actual)

Against the original forecast

  • Construction start2 months lateforecast Feb 5, 2005
  • Construction end17 months lateforecast Jun 30, 2006

Also in Orangeville

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 11746 in the federal list. How to read these figures.