Reconstruction of Two Bridges in the Township of Centre Wellington

Elora, Ontario

completeHighways and RoadsMRIF
Federal contribution
$1.1M
$1,079,440
Federal share33%

of $3.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 25, 2005
200620072008200920102011
Built
Program
Municipal Rural Infrastructure Fund
Construction start
Apr 20, 2005(actual)
Construction end
Dec 14, 2010(actual)

Against the original forecast

  • Construction end4 months earlyforecast Mar 31, 2011