Reconstruction of Two Bridges in the Township of Centre Wellington
Federal contribution
$1.1M
$1,079,440
Federal share33%
of $3.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 25, 2005
200620072008200920102011
Built
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Township of Centre Wellington
- Construction start
- Apr 20, 2005(actual)
- Construction end
- Dec 14, 2010(actual)
Against the original forecast
- Construction end4 months earlyforecast Mar 31, 2011
Also in Elora
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 11759 in the federal list. How to read these figures.