Back to projects

Reconstruction of Church Street (Elora)

Elora, Ontario

completeHighways and RoadsISF
Federal contribution
$412,172
Federal share31%

of $1.3M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Oct 15, 2009(actual)
Construction end
Mar 31, 2011(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Sep 15, 2009

Also in Elora

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 31069 in the federal list. How to read these figures.