Wastewater System Improvements

Saint-Louis-de-Kent, New Brunswick

completeWastewaterMRIF
Federal contribution
$400,000
Federal share33%

of $1.2M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedOct 31, 2004
ApprovedMar 24, 2005
2005200620072008
Built

Approved 5 months after the announcement.

Program
Municipal Rural Infrastructure Fund
Construction start
Mar 24, 2005(actual)
Construction end
Apr 7, 2008(actual)

Against the original forecast

  • Construction end20 months lateforecast Jul 31, 2006

Also in Saint-Louis-de-Kent

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 11769 in the federal list. How to read these figures.