Schedule

Announced and approvedAug 18, 2016
2017201820192020
Built
Program
Clean Water and Wastewater Fund
Construction start
Aug 14, 2017(actual)
Construction end
Oct 16, 2020(actual)

Against the original forecast

  • Construction start3 months lateforecast May 1, 2017
  • Construction end13 months lateforecast Sep 30, 2019