Water supply network - Reservoir, pumping stations and extensions
Saint-Louis-de-Kent, New Brunswick
Federal contribution
$1.7M
$1,690,779
Federal share50%
of $3.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 18, 2016
2017201820192020
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Village of Saint-Louis-de-Kent
- Construction start
- Aug 14, 2017(actual)
- Construction end
- Oct 16, 2020(actual)
Against the original forecast
- Construction start3 months lateforecast May 1, 2017
- Construction end13 months lateforecast Sep 30, 2019
Also in Saint-Louis-de-Kent
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47338 in the federal list. How to read these figures.