2,320projects·$1.8Bfederal of $3.8B eligible
Water pipe replacement
$37.4MMontréal · Drinking Water
complete·approved 2017
Cherry Street Stormwater and Lakefilling
$32.5MToronto · Wastewater
complete·approved 2016
CLRUSC Regional Water Supply System Extension
$32.4MBonnyville · Drinking Water
complete·approved 2016
North Red Deer Regional Wastewater Commission - Wastewater Transmission Line - Lacombe/Blackfalds to Red Deer Wastewater Treatment Plant
$29.9MLacombe · Wastewater
complete·approved 2016
Kelowna Integrated Water Project - Phase 1 (South East Kelowna Irrigation District/South Okanagan Mission Irrigation District Water Supply Project)
$26.4MKelowna · Drinking Water
complete·approved 2017
Rose Valley Water Treatment Plant
$24.7MWest Kelowna · Drinking Water
complete·approved 2017
Iqaluit Wastewater Upgrades
$19.9MIqaluit · Wastewater
complete·approved 2016
Water treatment, Lac-à-la-Tortue
$19.7MShawinigan · Drinking Water
complete·approved 2016
Second Feedermain to the Washburn Reservoir and Booster Station
$17.3MHalton · Drinking Water
complete·approved 2018
Water Infrastructure Upgrades in Arviat
$15.8MArviat · Drinking Water
underway·approved 2017
North Glengarry Regional Water Supply Task Force
$14.9MNorth Glengarry · Drinking Water
complete·approved 2017
Accelerated Corrugated metal pipe and water and sewer replacement.
$13.3MYellowknife · Wastewater
complete·approved 2016
Rehabilitation of the York-Durham Sewer on 16th Avenue the City of Markham
$12.1MYork · Wastewater
complete·approved 2018
Project Scotland
$11.2MLethbridge · Wastewater
complete·approved 2017
Robert O. Picard Environmental Center Thickening and Dewatering Building Heating, Ventilation and Air Conditioning Upgrade
$9.9MOttawa · Wastewater
complete·approved 2018
Implementation of Improvements to the Water Supply System in Mississauga
$9.1MPeel · Drinking Water
complete·approved 2017
West Corridor Water Transmission Line Phase 1 - Wembley
$9.0MWembley · Drinking Water
complete·approved 2016
County of Vermilion River - Stage 4 Regional Waterline Lloydminster to Kitscoty
$8.9MKitscoty · Drinking Water
complete·approved 2016
Storm sewers - Laurentienne and Félix-Leclerc Highways
$8.2MQuébec · Wastewater
complete·approved 2017
Northwest arm sewer rehabilitation
$8.2MHalifax · Wastewater
complete·approved 2016
Village of Rockyford - Wheatland Regional - Phase 2 - WTP Upgrade/Waterline to Rockyford
$8.2MRockyford · Drinking Water
complete·approved 2016
Vermilion Wastewater Treatment Plant Ugrade
$8.0MVermilion · Wastewater
complete·approved 2017
Harmony Creek Water Pollution Control Plant Upgrades
$7.8MDurham · Wastewater
complete·approved 2017
Extension of the sanitary sewer system - Eastern sector
$7.7MNeuville · Wastewater
complete·approved 2016
Structural lining of 17km of watermains in 29 locations in Toronto
$7.5MToronto · Drinking Water
complete·approved 2017
Third Force Main Upgrade to McCarthy Blvd Pump Station
$7.5MRegina · Wastewater
complete·approved 2016
Sewer Outfall Replacement
$7.5MInuvik · Wastewater
complete·approved 2016
Replacement of Water Mains in Peel
$7.5MPeel · Drinking Water
complete·approved 2017
New Wells and Water Supply Pipeline at Melville
$6.9MMelville · Drinking Water
complete·approved 2017
Upgrading the Filtration Plant
$6.9MSaint-Hyacinthe · Drinking Water
complete·approved 2016
West Inter-Lake District Regional Waterline Phase 2 to Onoway and Gunn
$6.8MOnoway · Drinking Water
complete·approved 2016
Arsenic and Manganese Water Treatment
$6.8MWhite Rock · Drinking Water
complete·approved 2017
Charlottetown Pollution Control Plant Upgrades
$6.3MCharlottetown · Wastewater
complete·approved 2017
New Water Treatment Plant and Regional Pipelines Russell-Binscarth
$6.2MRussell-Binscarth≈ · Drinking Water
complete·approved 2016
Culvert Renewal Program at Various Locations Across the City - Replacement of 121 culverts
$6.0MOttawa · Wastewater
complete·approved 2018
New River Street Water Reservoir
$6.0MPrince Albert · Drinking Water
complete·approved 2017
Watermain Rehabilitation
$6.0MCape Breton · Drinking Water
complete·approved 2016
Drinking water supply, production and distribution systems
$6.0MSainte-Anne-de-Beaupré · Drinking Water
complete·approved 2017
Waste Pollution Control Facility Upgrades - Phase 1 - LRAR
$5.9MPortage la Prairie · Wastewater
complete·approved 2017
Vancouver South Sewer Separation
$5.8MVancouver · Wastewater
complete·approved 2017
Water and Wastewater Upgrades
$5.7MDawson City · Drinking Water
complete·approved 2016
St. Paul Wastewater Treatment Plant Upgrades
$5.5MSt. Paul · Wastewater
complete·approved 2017
Town of Stratford Wastewater Delivery System to the Charlottetown Pollution Control Plant
$5.5MStratford · Wastewater
complete·approved 2017
Drinking water supply - Connection to Drummondville
$5.4MSaint-Cyrille-de-Wendover · Drinking Water
complete·approved 2017
Sanitary Servicing to Reduce Phosphorus to Lake Simcoe- Royal Oak, Bay, Cottage Lane
$5.3MBarrie · Wastewater
complete·approved 2018
Ladysmith Drinking Water Filtration
$5.3MLadysmith · Drinking Water
complete·approved 2016
CRPWSC Waterline Twinning Phase 1 CFRN to Acheson
$5.1MSpruce Grove · Drinking Water
complete·approved 2017
Mountain Trunk Storm Sewer - Structural rehabilitation and repairs of 400 meters of 4.5 meter by 5.4 meter arch shaped concrete storm sewer to prevent imminent collapse
$5.0MHamilton · Wastewater
complete·approved 2017
Supplemental Water Supply System
$5.0MSteinbach · Drinking Water
complete·approved 2017
Electrical Upgrades at the Hanlan and Herridge Pumping Stations
$5.0MPeel · Drinking Water
complete·approved 2017
| Project | Location | Category | Status | Federal | Total | Approved |
|---|---|---|---|---|---|---|
| Water pipe replacement City of Montréal | Montréal | Drinking Water | complete | $37.4M | $74.9M | 2017 |
| Cherry Street Stormwater and Lakefilling City of Toronto | Toronto | Wastewater | complete | $32.5M | $65.0M | 2016 |
| CLRUSC Regional Water Supply System Extension Town of Bonnyville | Bonnyville | Drinking Water | complete | $32.4M | $64.9M | 2016 |
| North Red Deer Regional Wastewater Commission - Wastewater Transmission Line - Lacombe/Blackfalds to Red Deer Wastewater Treatment Plant North Red Deer Regional Wastewater Commission (NRDRWC) | Lacombe | Wastewater | complete | $29.9M | $59.8M | 2016 |
| Kelowna Integrated Water Project - Phase 1 (South East Kelowna Irrigation District/South Okanagan Mission Irrigation District Water Supply Project) City of Kelowna | Kelowna | Drinking Water | complete | $26.4M | $52.9M | 2017 |
| Rose Valley Water Treatment Plant District of West Kelowna | West Kelowna | Drinking Water | complete | $24.7M | $49.4M | 2017 |
| Iqaluit Wastewater Upgrades City of Iqaluit | Iqaluit | Wastewater | complete | $19.9M | $26.5M | 2016 |
| Water treatment, Lac-à-la-Tortue City of Shawinigan | Shawinigan | Drinking Water | complete | $19.7M | $39.4M | 2016 |
| Second Feedermain to the Washburn Reservoir and Booster Station Corporation of the Regional Municipality of Halton | Halton | Drinking Water | complete | $17.3M | $45.0M | 2018 |
| Water Infrastructure Upgrades in Arviat Government of Nunavut | Arviat | Drinking Water | underway | $15.8M | $21.0M | 2017 |
| North Glengarry Regional Water Supply Task Force Township of North Glengarry | North Glengarry | Drinking Water | complete | $14.9M | $30.0M | 2017 |
| Accelerated Corrugated metal pipe and water and sewer replacement. City of Yellowknife | Yellowknife | Wastewater | complete | $13.3M | $18.3M | 2016 |
| Rehabilitation of the York-Durham Sewer on 16th Avenue the City of Markham Regional Municipality of York | York | Wastewater | complete | $12.1M | $24.3M | 2018 |
| Project Scotland City of Lethbridge | Lethbridge | Wastewater | complete | $11.2M | $22.4M | 2017 |
| Robert O. Picard Environmental Center Thickening and Dewatering Building Heating, Ventilation and Air Conditioning Upgrade City of Ottawa | Ottawa | Wastewater | complete | $9.9M | $19.9M | 2018 |
| Implementation of Improvements to the Water Supply System in Mississauga Regional Municipality of Peel | Peel | Drinking Water | complete | $9.1M | $18.3M | 2017 |
| West Corridor Water Transmission Line Phase 1 - Wembley Town of Wembley | Wembley | Drinking Water | complete | $9.0M | $18.1M | 2016 |
| County of Vermilion River - Stage 4 Regional Waterline Lloydminster to Kitscoty Municipal District of Vermilion River | Kitscoty | Drinking Water | complete | $8.9M | $19.1M | 2016 |
| Storm sewers - Laurentienne and Félix-Leclerc Highways City of Québec | Québec | Wastewater | complete | $8.2M | $16.4M | 2017 |
| Northwest arm sewer rehabilitation Halifax Regional Water Commission | Halifax | Wastewater | complete | $8.2M | $16.3M | 2016 |
| Village of Rockyford - Wheatland Regional - Phase 2 - WTP Upgrade/Waterline to Rockyford Village of Rockyford | Rockyford | Drinking Water | complete | $8.2M | $17.9M | 2016 |
| Vermilion Wastewater Treatment Plant Ugrade Town of Vermilion | Vermilion | Wastewater | complete | $8.0M | $16.2M | 2017 |
| Harmony Creek Water Pollution Control Plant Upgrades Regional Municipality of Durham | Durham | Wastewater | complete | $7.8M | $15.5M | 2017 |
| Extension of the sanitary sewer system - Eastern sector Village of Neuville | Neuville | Wastewater | complete | $7.7M | $15.4M | 2016 |
| Structural lining of 17km of watermains in 29 locations in Toronto City of Toronto | Toronto | Drinking Water | complete | $7.5M | $20.0M | 2017 |
| Third Force Main Upgrade to McCarthy Blvd Pump Station City of Regina | Regina | Wastewater | complete | $7.5M | $15.0M | 2016 |
| Sewer Outfall Replacement Town of Inuvik | Inuvik | Wastewater | complete | $7.5M | $10.0M | 2016 |
| Replacement of Water Mains in Peel Regional Municipality of Peel | Peel | Drinking Water | complete | $7.5M | $15.0M | 2017 |
| New Wells and Water Supply Pipeline at Melville SaskWater | Melville | Drinking Water | complete | $6.9M | $13.8M | 2017 |
| Upgrading the Filtration Plant City of Saint-Hyacinthe | Saint-Hyacinthe | Drinking Water | complete | $6.9M | $13.7M | 2016 |
| West Inter-Lake District Regional Waterline Phase 2 to Onoway and Gunn West Inter-Lake District Regional Water Commission (WILD) | Onoway | Drinking Water | complete | $6.8M | $13.7M | 2016 |
| Arsenic and Manganese Water Treatment City of White Rock | White Rock | Drinking Water | complete | $6.8M | $13.6M | 2017 |
| Charlottetown Pollution Control Plant Upgrades City of Charlottetown | Charlottetown | Wastewater | complete | $6.3M | $12.7M | 2017 |
| New Water Treatment Plant and Regional Pipelines Russell-Binscarth Rural Municipality of Russel-Binscarth | Russell-Binscarth≈ | Drinking Water | complete | $6.2M | $13.0M | 2016 |
| Culvert Renewal Program at Various Locations Across the City - Replacement of 121 culverts City of Ottawa | Ottawa | Wastewater | complete | $6.0M | $12.4M | 2018 |
| New River Street Water Reservoir City of Prince Albert | Prince Albert | Drinking Water | complete | $6.0M | $12.0M | 2017 |
| Watermain Rehabilitation Regional Municipality of Cape Breton | Cape Breton | Drinking Water | complete | $6.0M | $12.0M | 2016 |
| Drinking water supply, production and distribution systems City of Sainte-Anne-de-Beaupré | Sainte-Anne-de-Beaupré | Drinking Water | complete | $6.0M | $11.9M | 2017 |
| Waste Pollution Control Facility Upgrades - Phase 1 - LRAR City of Portage La Prairie | Portage la Prairie | Wastewater | complete | $5.9M | $28.8M | 2017 |
| Vancouver South Sewer Separation City of Vancouver | Vancouver | Wastewater | complete | $5.8M | $11.7M | 2017 |
| Water and Wastewater Upgrades City of Dawson | Dawson City | Drinking Water | complete | $5.7M | $8.1M | 2016 |
| St. Paul Wastewater Treatment Plant Upgrades Town of St. Paul | St. Paul | Wastewater | complete | $5.5M | $11.1M | 2017 |
| Town of Stratford Wastewater Delivery System to the Charlottetown Pollution Control Plant Town of Stratford | Stratford | Wastewater | complete | $5.5M | $10.9M | 2017 |
| Drinking water supply - Connection to Drummondville Municipality of Saint-Cyrille-de-Wendover | Saint-Cyrille-de-Wendover | Drinking Water | complete | $5.4M | $13.3M | 2017 |
| Sanitary Servicing to Reduce Phosphorus to Lake Simcoe- Royal Oak, Bay, Cottage Lane City of Barrie | Barrie | Wastewater | complete | $5.3M | $10.9M | 2018 |
| Ladysmith Drinking Water Filtration Town of Ladysmith | Ladysmith | Drinking Water | complete | $5.3M | $10.6M | 2016 |
| CRPWSC Waterline Twinning Phase 1 CFRN to Acheson City of Spruce Grove | Spruce Grove | Drinking Water | complete | $5.1M | $24.0M | 2017 |
| Mountain Trunk Storm Sewer - Structural rehabilitation and repairs of 400 meters of 4.5 meter by 5.4 meter arch shaped concrete storm sewer to prevent imminent collapse City of Hamilton | Hamilton | Wastewater | complete | $5.0M | $10.5M | 2017 |
| Supplemental Water Supply System City of Steinbach | Steinbach | Drinking Water | complete | $5.0M | $10.0M | 2017 |
| Electrical Upgrades at the Hanlan and Herridge Pumping Stations Regional Municipality of Peel | Peel | Drinking Water | complete | $5.0M | $10.0M | 2017 |