Kelowna Integrated Water Project - Phase 1 (South East Kelowna Irrigation District/South Okanagan Mission Irrigation District Water Supply Project)

Kelowna, British Columbia

completeDrinking WaterCWWF
Federal contribution
$26.4M
$26,450,000
Federal share50%

of $52.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 17, 2017
201820192020
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Kelowna
Construction start
Oct 2, 2017(actual)
Construction end
Mar 31, 2020(actual)

Against the original forecast

  • Construction start9 months earlyforecast Jul 6, 2018