Kelowna Integrated Water Project - Phase 1 (South East Kelowna Irrigation District/South Okanagan Mission Irrigation District Water Supply Project)
Federal contribution
$26.4M
$26,450,000
Federal share50%
of $52.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 17, 2017
201820192020
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Kelowna
- Construction start
- Oct 2, 2017(actual)
- Construction end
- Mar 31, 2020(actual)
Against the original forecast
- Construction start9 months earlyforecast Jul 6, 2018