Highway 97 - Highway 33 to Edwards
Federal contribution
$18.0M
$18,000,000
Federal share44%
of $40.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 15, 2013
20142015201620172018
Built
Approved 3 months after the announcement.
- Program
- Building Canada Fund - Major Infrastructure Component
- Ultimate recipient
- British Columbia Transit
- Construction start
- Apr 1, 2015(actual)
- Construction end
- Aug 1, 2018(actual)
Against the original forecast
- Construction end12 months earlyforecast Jul 31, 2019
Also in Kelowna
- Kelowna Integrated Water Project - Phase 1 (South East Kelowna Irrigation District/South Okanagan Mission Irrigation District Water Supply Project)$26.4M
- Kelowna RapidBus Transit$7.0M
- Kelowna - Septic System Elimination and Sewer Connection$4.9M
- Kelowna - Mission Creek Bridge$4.0M
- Kelowna - Active Transportation Network$3.8M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 44304 in the federal list. How to read these figures.