Kelowna - Mission Creek Bridge

Kelowna, British Columbia

completeHighways and RoadsISF
Federal contribution
$4.0M
$4,028,105
Federal share26%

of $15.6M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedApr 7, 2009
ApprovedJan 25, 2010
20102011
Built

Approved 10 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Kelowna
Construction start
May 1, 2010(actual)
Construction end
Nov 4, 2011(actual)

Against the original forecast

  • Construction start9 months lateforecast Aug 1, 2009