Kelowna RapidBus Transit

Kelowna, British Columbia

completePublic TransitMIC
Federal contribution
$7.0M
$6,999,883
Federal share21%

of $32.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 15, 2013
20122013201420152016
Built

Approved 2 years before the announcement.

Program
Building Canada Fund - Major Infrastructure Component
Construction start
Dec 2, 2013(actual)
Construction end
Mar 1, 2016(actual)

Against the original forecast

  • Construction start2.3 years lateforecast Aug 5, 2011
  • Construction end2 months lateforecast Dec 31, 2015

Also in Kelowna

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29932 in the federal list. How to read these figures.