Kelowna - Septic System Elimination and Sewer Connection
Federal contribution
$4.9M
$4,928,000
Federal share40%
of $12.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 12, 2021
2022202320242025
Built
Approved 3 weeks before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- City of Kelowna
- Construction start
- Nov 9, 2021(actual)
- Construction end
- Dec 5, 2024(actual)
Against the original forecast
- Construction start17 months earlyforecast Apr 11, 2023
- Construction end12 months earlyforecast Dec 19, 2025
Also in Kelowna
- Kelowna Integrated Water Project - Phase 1 (South East Kelowna Irrigation District/South Okanagan Mission Irrigation District Water Supply Project)$26.4M
- Highway 97 - Highway 33 to Edwards$18.0M
- Kelowna RapidBus Transit$7.0M
- Kelowna - Mission Creek Bridge$4.0M
- Kelowna - Active Transportation Network$3.8M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60850 in the federal list. How to read these figures.