Back to projects

West Corridor Water Transmission Line Phase 1 - Wembley

Wembley, Alberta

completeDrinking WaterCWWF
Federal contribution
$9.0M
$9,045,000
Federal share50%

of $18.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 1, 2016
2017201820192020
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Wembley
Construction start
Jan 15, 2018(actual)
Construction end
Dec 31, 2019(actual)

Against the original forecast

  • Construction start14 months lateforecast Nov 1, 2016
  • Construction end2 months lateforecast Oct 31, 2019

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47595 in the federal list. How to read these figures.