Mountain Trunk Storm Sewer - Structural rehabilitation and repairs of 400 meters of 4.5 meter by 5.4 meter arch shaped concrete storm sewer to prevent imminent collapse
Federal contribution
$5.0M
$5,001,220
Federal share48%
of $10.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 23, 2017
201820192020
Built
Approved 6 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Hamilton
- Construction start
- Apr 1, 2017(actual)
- Construction end
- Mar 31, 2020(actual)
Against the original forecast
- Construction start8 weeks lateforecast Feb 1, 2017
- Construction end6 months lateforecast Sep 30, 2019