Back to projects

Mountain Trunk Storm Sewer - Structural rehabilitation and repairs of 400 meters of 4.5 meter by 5.4 meter arch shaped concrete storm sewer to prevent imminent collapse

Hamilton, Ontario

completeWastewaterCWWF
Federal contribution
$5.0M
$5,001,220
Federal share48%

of $10.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 23, 2017
201820192020
Built

Approved 6 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Hamilton
Construction start
Apr 1, 2017(actual)
Construction end
Mar 31, 2020(actual)

Against the original forecast

  • Construction start8 weeks lateforecast Feb 1, 2017
  • Construction end6 months lateforecast Sep 30, 2019

Also in Hamilton

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48688 in the federal list. How to read these figures.