Improvements to the Woodward Avenue wastewater treatment plant
Federal contribution
$100.0M
$100,000,000
Federal share30%
of $337.3M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMar 12, 2012
ApprovedOct 9, 2013
20122015201820212024
BuiltForecast
Approved 19 months after the announcement.
- Program
- Green Infrastructure Fund
- Ultimate recipient
- City of Hamilton
- Construction start
- May 15, 2017(actual)
- Construction end
- Mar 31, 2024(forecast)
Against the original forecast
- Construction start13 months earlyforecast Jun 1, 2018