Replacement of Transit Fleet
Federal contribution
$45.6M
$45,630,800
Federal share40%
of $114.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 19, 2021
today
2022202420262028
BuiltForecast
Approved 6 weeks before the announcement.
- Program
- Public Transit Infrastructure Stream
- Ultimate recipient
- City of Hamilton
- Construction start
- Dec 16, 2021(actual)
- Construction end
- Mar 31, 2028(forecast)
Against the original forecast
- Construction start2 weeks earlyforecast Dec 31, 2021
Also in Hamilton
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57260 in the federal list. How to read these figures.