Third Force Main Upgrade to McCarthy Blvd Pump Station

Regina, Saskatchewan

completeWastewaterCWWF
Federal contribution
$7.5M
$7,500,000
Federal share50%

of $15.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 16, 2016
20172018
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Regina
Construction start
Feb 15, 2017(actual)
Construction end
Apr 10, 2018(actual)

Against the original forecast

  • Construction start2 months earlyforecast May 1, 2017
  • Construction end15 months earlyforecast Jun 30, 2019

Also in Regina

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47649 in the federal list. How to read these figures.