Replacement of Water Mains in Peel
Federal contribution
$7.5M
$7,496,962
Federal share50%
of $15.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 23, 2017
20182019
Built
Approved 3 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Regional Municipality of Peel
- Construction start
- Jun 7, 2017(actual)
- Construction end
- Jan 31, 2019(actual)
Against the original forecast
- Construction start6 weeks earlyforecast Jul 17, 2017
- Construction end6 months lateforecast Jul 31, 2018
Also in Peel
- Implementation of Improvements to the Water Supply System in Mississauga$9.1M
- Electrical Upgrades at the Hanlan and Herridge Pumping Stations$5.0M
- Construction of a New 750-mm Water Main on Goreway Drive$5.0M
- Equipment Replacement at the G.E. Booth Water Pollution Control Plant$4.9M
- Condition Assessment of the Region's Storm Sewer Infrastructure$4.0M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48557 in the federal list. How to read these figures.