Drinking water supply - Connection to Drummondville
Saint-Cyrille-de-Wendover, Quebec
Federal contribution
$5.4M
$5,399,491
Federal share40%
of $13.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 20, 2017
2018
Built
Approved 2 months before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Municipality of Saint-Cyrille-de-Wendover
- Construction start
- Aug 1, 2017(actual)
- Construction end
- Nov 15, 2018(actual)
Against the original forecast
- Construction start3 months lateforecast May 15, 2017