CRPWSC Waterline Twinning Phase 1 CFRN to Acheson
Federal contribution
$5.1M
$5,051,425
Federal share21%
of $24.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 6, 2017
20182019202020212022
Built
Approved 5 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Spruce Grove
- Construction start
- May 9, 2017(actual)
- Construction end
- Jul 1, 2022(actual)
Against the original forecast
- Construction start5 weeks lateforecast Apr 1, 2017
- Construction end6 months lateforecast Dec 31, 2021
Also in Spruce Grove
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49894 in the federal list. How to read these figures.