CRPWSC Waterline Twinning Phase 1 CFRN to Acheson

Spruce Grove, Alberta

completeDrinking WaterCWWF
Federal contribution
$5.1M
$5,051,425
Federal share21%

of $24.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 6, 2017
20182019202020212022
Built

Approved 5 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Spruce Grove
Construction start
May 9, 2017(actual)
Construction end
Jul 1, 2022(actual)

Against the original forecast

  • Construction start5 weeks lateforecast Apr 1, 2017
  • Construction end6 months lateforecast Dec 31, 2021