Back to projects

Spruce Grove Electronic Council Meeting Management Software and Council Chambers Upgrade

Spruce Grove, Alberta

completeVentilationCVRIS
Federal contribution
$246,173
Federal share80%

of $307.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 16, 2021
Built

Approved 4 weeks before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
City of Spruce Grove
Construction start
Jun 21, 2021(actual)
Construction end
Sep 19, 2021(actual)

Against the original forecast

  • Construction start4 months lateforecast Feb 15, 2021
  • Construction end13 months earlyforecast Oct 31, 2022

Also in Spruce Grove

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58508 in the federal list. How to read these figures.