Spruce Grove Transit Hub/Park and Ride
Federal contribution
$404,550
Federal share14%
of $2.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 12, 2021
202220232024
Built
- Program
- Public Transit Infrastructure Stream
- Ultimate recipient
- City of Spruce Grove
- Construction start
- Nov 23, 2022(actual)
- Construction end
- Nov 4, 2024(actual)
Against the original forecast
- Construction start4 months lateforecast Aug 2, 2022
Also in Spruce Grove