Extension of the sanitary sewer system - Eastern sector
Federal contribution
$7.7M
$7,677,717
Federal share50%
of $15.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 1, 2017
2017201820192020
Built
Approved 2 months before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Village of Neuville
- Construction start
- Aug 24, 2018(actual)
- Construction end
- Feb 28, 2020(actual)
Against the original forecast
- Construction start5 months lateforecast Apr 2, 2018
- Construction end5 weeks earlyforecast Mar 31, 2020
Also in Neuville
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48936 in the federal list. How to read these figures.