Extension of the sanitary sewer system - Eastern sector

Neuville, Quebec

completeWastewaterCWWF
Federal contribution
$7.7M
$7,677,717
Federal share50%

of $15.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 1, 2017
2017201820192020
Built

Approved 2 months before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Village of Neuville
Construction start
Aug 24, 2018(actual)
Construction end
Feb 28, 2020(actual)

Against the original forecast

  • Construction start5 months lateforecast Apr 2, 2018
  • Construction end5 weeks earlyforecast Mar 31, 2020